canada
by a flotation device ,” says Doug Keating , mine manager at Dufferin . “ We are hitting 300 tons a day and we should be able to double that by 2016 .”
Existing mining infrastructure on site includes permits , gravity and flotation processes , underground access , surface infrastructure in place , and accessible roads . The 100 percent underground mine is comprised of core drilling and some surface drilling for exploration purposes .
In June , Ressources Appalaches announced its crushing unit and processing plant had begun processing ore at the Dufferin site .
According to CEO Alain Hupe , “ producing ore from a second face at vein # 1 , the start of the crushing unit and gravity line at the Dufferin processing plant are all very significant steps to produce the first Dore during May . Following this
“ We currently employ a gravity circuit at the mine , recovering 75 percent of resources and the other 25 percent being recovered by a flotation device ,” says Doug Keating , mine manager at Dufferin . “ We are hitting 300 tons a day and we should be able to double that by 2016 .”
www . ressourcesappalaches . com 165